- 5
- steps per request
- 0
- work starts before a decision
Handle scope creep by logging every request outside the brief before you start it. Note who asked, what they asked for, the extra hours and fee, the days it adds, and the client's decision. The request stays Pending, and unstarted, until someone decides. The log records decisions. It is not a legal document.
What is scope creep?
Scope creep is work added after the brief was agreed, with no change to price or dates.
It rarely arrives as one big demand. It arrives as small extras that each feel too minor to mention. Added up, they become a project nobody quoted.
How does a scope change log work?
Keep one table per project. Each request outside the brief gets one row. The row moves through a fixed set of statuses. There are five steps:
Notice
Compare the request with the brief. If the brief covers it, it is not a change.
Log it
Add the date, who asked, and their words. Do this before you start.
Price it
Estimate hours, multiply by your rate, note any days added.
Send options
Show the cost and the dates. Let the client choose.
Record it
Mark it Approved, Declined or Pending. Update the dates.
The fee is simple arithmetic. Write the formula down so the client can follow it:
Extra fee = extra hours x hourly rate
What does a scope change log look like?
This sample uses invented data and a rate of 65 per hour. It matches the kit's workbook. SC-01 and SC-02 were outside the brief. SC-03 sat inside revision round 1.
| ID | Request | Extra hours | Extra fee | Days added | Status |
|---|---|---|---|---|---|
| SC-01 | Add a catering page with its own enquiry form | 5.0 | 325.00 | 4 | Approved |
| SC-02 | Add an online payment option for orders | 12.0 | 780.00 | 10 | Pending |
| SC-03 | Change the menu photo crop on the home page | 0.0 | 0.00 | 0 | Declined |
Look at the last row. SC-03 was logged but declined as a change. It is a normal revision inside the included rounds, so it costs nothing. Logging it still shows the client you checked.
In this sample, one request is Pending. It is worth 780.00, and nothing on it has started.
How do you tell a revision from a scope change?
A revision changes how something in the brief looks or reads. A scope change adds something the brief did not include.
Can you point to a deliverable in the brief that the request improves? Then it is a revision. If you cannot, it is a change.
| Request | Usually | Why |
|---|---|---|
| Make the heading larger and change the button colour | Revision | It adjusts an existing page. |
| Rewrite the About text we already approved | Revision or change | A revision if a round is left. A change if the text was approved and needs a new round. |
| Add a booking form | Scope change | A new feature, not in the brief. |
| Add three more pages | Scope change | New deliverables and new hours. |
| Redo the layout after sign-off | Scope change | Approved work is being reopened. |
Your brief and revision allowance settle the borderline cases. Write them down at the start. Count rounds the same way each time: one set of feedback on one version is one round.
What should you say to the client?
Keep it factual. Give them a choice. For example:
Hi [Client first name], thanks for the idea about [request]. It is outside the agreed brief, so I have logged it as a change instead of fitting it in quietly. I estimate [hours] hours. That is [fee], and it would move the launch date by [days] days.
A) Add it, with that fee and date. B) Swap it for [item in brief]. C) Leave it out for now. Tell me which you prefer. I will not start until you do.
Option B matters. Clients often have a fixed budget. Many would happily trade one item for another, but never knew they could.
What if the client does not answer?
The request stays Pending and you do not start it. A Pending row keeps its value in the log summary, so the open decision does not vanish.
If the missing answer blocks a milestone, say so: "The launch date depends on SC-02. If I do not hear by [date], I will leave it out and keep the original date." Then do exactly that.
What does a scope change log not do?
- It does not replace a contract. An entry records a decision. It is not a legal change order. Have your own adviser review any terms.
- It does not make a client accept a price. It shows the price and date before the work, when a disagreement is cheapest.
- It does not fix an unclear brief. If exclusions were never written down, you will have more borderline cases.
Where can you get a ready-made scope change log?
The Client Delivery Kit has a Scope changes sheet. It works out each extra fee. It adds up Pending and Approved value and the days added. It also has a Scope change message script.
The sheet pairs with the Brief sheet, so the exclusions you wrote at the start are the ones you check requests against. You can try the quote logic in the free calculator. For the first week of a project, read the client onboarding checklist.
I built the workbook and checked its formulas against a separate calculation in LibreOffice. Check dropdowns and date formats if you use it in Excel or Google Sheets.